As the title says we are doing a reno that requires new point loads for beams on the main floor. And of course one of the has old clay running threw it. The clay was broken durning the dig. What we want to do is just join the clay back together with 4" PVC and couplings then just pour the point load around it. So the question is can we do that or do we need to completely reroute the drain around the new point load.
Thanks Karlyle