dan Dragomir
New Member
Hello, I doing my own remodeling and I decided to apply for permits,
I had a designer drawn up the kitchen plans and I have a little bit of problem with my township,
While they will allow me to do the work they are asking me to provide them with
I had a designer drawn up the kitchen plans and I have a little bit of problem with my township,
While they will allow me to do the work they are asking me to provide them with
- Riser Diagram for Gas Line ( the gas range is been relocated and they are saying that any appliances that are new or been relocated will require a complete gaspipe riser diagram showing existing and proposed gas pipe, the type of pipe been used and the size and lengt of each segment of the pipe, btu load of each appliance and the gasline should be tested .
- Laundry room is been relocated from 1st floor to 2nd floor - Waterline and Wasteline isometric riser diagrams will be needed showing the proposed new plumbing and where the connections will be