teddyk
New Member
- Messages
- 2
- Reaction score
- 0
- Points
- 1
I've read quite a few posts on the site in regards to this but I guess I require more specific advice about switching my system to PEX. I like Tom Sawyers advice on a lot of the threads and hope you respond.
I have a older 2400 sqf home in Ontario, Canada, built in 1927. we've done a lot of reno's and have spray foamed 3 of the rooms while walls were open. The house has 4 finished floors which includes a finished attic with 2 rads. We just had the old boiler pulled out along with asbestos abatement. I now have a Lennox 150 BTU boiler and 2 Wilo pumps along with this 10 loop manifold.
All the steel pipe in the basement has been removed due to the abatement, I wanted them out. The steel pipe was 1 1/4" - 2". I have direct access to run pex from the manifold to all the rads in the basement and the main floor, most on individual loops. I don't see this as an issue considering they will almost all be home run. My issue is with 4 runs that go to the 2nd and 3rd floor and if I should use pex on the runs or use steel for these to make sure they get the flow they need since 3 of the 4 runs feed 2 rads each. See below.
1 run feeds a laundry room on the second floor and that's it. The steel left in the walls is 1".
2 runs each feed a bedroom on the second floor and one on the third floor and are 1 1/4" pipe in the walls.
1 run feeds a bathroom on the second floor where I have converted to a hydronic towel bar and the lines up the wall are 1 1/4"
I've been told by 2 contractors that I should go to either 1 1/4" steel or copper on a 3 loops system to supply each floor separately and that the 1/2 pex would not be sufficient to heat the 2nd and 3rd floors. However I figure since almost all will be home runs, except for the 3 that feed 2 rooms each I should be ok with just running 1/2 pex from the manifold and feeding the rads directly or tying into the 1 - 1 1/4" steel. I would also like to put the pump on the supply side as I've heard reduces air in the system. I would like to replace the 1 and 1 1/4 steel in the walls in the next few years but just need to get the heat on right now
Advice would be GREATLY appreciated, it's getting cold out and the wife is not happy with my timing on this...
Thanks
I have a older 2400 sqf home in Ontario, Canada, built in 1927. we've done a lot of reno's and have spray foamed 3 of the rooms while walls were open. The house has 4 finished floors which includes a finished attic with 2 rads. We just had the old boiler pulled out along with asbestos abatement. I now have a Lennox 150 BTU boiler and 2 Wilo pumps along with this 10 loop manifold.
All the steel pipe in the basement has been removed due to the abatement, I wanted them out. The steel pipe was 1 1/4" - 2". I have direct access to run pex from the manifold to all the rads in the basement and the main floor, most on individual loops. I don't see this as an issue considering they will almost all be home run. My issue is with 4 runs that go to the 2nd and 3rd floor and if I should use pex on the runs or use steel for these to make sure they get the flow they need since 3 of the 4 runs feed 2 rads each. See below.
1 run feeds a laundry room on the second floor and that's it. The steel left in the walls is 1".
2 runs each feed a bedroom on the second floor and one on the third floor and are 1 1/4" pipe in the walls.
1 run feeds a bathroom on the second floor where I have converted to a hydronic towel bar and the lines up the wall are 1 1/4"
I've been told by 2 contractors that I should go to either 1 1/4" steel or copper on a 3 loops system to supply each floor separately and that the 1/2 pex would not be sufficient to heat the 2nd and 3rd floors. However I figure since almost all will be home runs, except for the 3 that feed 2 rooms each I should be ok with just running 1/2 pex from the manifold and feeding the rads directly or tying into the 1 - 1 1/4" steel. I would also like to put the pump on the supply side as I've heard reduces air in the system. I would like to replace the 1 and 1 1/4 steel in the walls in the next few years but just need to get the heat on right now
Advice would be GREATLY appreciated, it's getting cold out and the wife is not happy with my timing on this...
Thanks