We have the following layout for a basement rough-in. In reviewing the placement of the water closest, 2" shower drain, and the lavatory I'm confused on how to layout the three. It appears to me that they have missed placed the 2" shower drain as I don't have enough room for all three. Any ideas on how to get all three items into a bathroom? There are no walls yet so we are free to place them anywhere. Except for the concrete walls which are what are depicted in the drawing.
If the 2" drain is in the way, I can remove it as it's not required. Is the best way to remove it to cut it off slightly below surface level, stuff it with a rag and then fill over the top with concrete?
P.S. I'm hoping that I have the image import figured out.
If the 2" drain is in the way, I can remove it as it's not required. Is the best way to remove it to cut it off slightly below surface level, stuff it with a rag and then fill over the top with concrete?
P.S. I'm hoping that I have the image import figured out.