    Hi,

    I'm looking for advice on replacing a sewer main buried in the concrete slab. This is not a basement it is an old structure with a slab. If the worst case scenario develops and I have to remove the whole thing or replace new somewhere else, what is the best technique for removing the concrete to get down to a level good enough for the new sewer line? What tools would you guys recommend?

    Thanks for any replys!
  2. ArtM

    ArtM Junior Member

    Messages:
    9
    Location:
    East Slope of the Rockies
    Well, the concrete is only a small part of the work. It's all the dirt you may need to move under the concrete that gets tiring. And then, to do it right you need a gravel bed before the new line install, and then some more gravel and a whole bunch of dirt to fill in the trench.

    You haven't given much details to work with. Commercial building? Old residence of some kind? Are there many partition walls in the building? Can you open one end of the building and get a small backhoe inside? Then again, can you put the new line outside along the building - only going under the slab where you need to, so that the slab is compromised as little as possible?

    Every building is different - and each may have a different best solution.

    The common way to make sewer repairs under a slab is to try and map the lines - and then cut paths in the concrete over the top of them - a cut 8 to 12 inches each side of the pipe. The width of the "path" will depend on the line size and how the dirt is removed. Then the paths are broken up by jack hammer or hand sledge and the concrete debris removed. Now comes the fun part - shovel work, more often than not. The last one we did was an an old apartment house and the concrete floor covering all the sewer lines was in the basement. Lots and lots of shovel and wheel-barrow work - running the wheel-barrow up a ramp on the stairs. The worst part was the old lines that had to be removed were buried in wet gumbo. Arggh! What a pain.

    Hard to tell you much about your situation without more details on the building.
  3. hj

    hj Moderator & Master Plumber Staff Member

    Messages:
    26,815
    Location:
    Cave Creek, Arizona
    concete

    If you know the direction of the pipe, then saw cutting it and removing the concrete is the only good way to do it. Otherwise you have to follow the pipe by breaking and digging as you go. The best tool for this work, in this area, is a couple of illegals and a jack hammer.

    [​IMG]
    Last edited by a moderator: Dec 15, 2009
Similar Threads: Worst Case
Forum Title Date
Plumbing Forum, Professional & DIY Advice Pig Slop Contest. Who found the worst plumbing? Jan 16, 2010
Plumbing Forum, Professional & DIY Advice The worst I have seen in a long time May 27, 2007
Plumbing Forum, Professional & DIY Advice Advice on adding a drain, just in case the washer does something wonky Jan 11, 2014
Plumbing Forum, Professional & DIY Advice Can I encase Under slab 2" ABS In concrete Mar 26, 2010
Plumbing Forum, Professional & DIY Advice Case wall mount 1100 toilet Jan 26, 2010

Share This Page