alanmeyer
New Member
Hi,
I'm attempting a DIY installation of a water softener. One problem is that the water softener needs to be mounted about 30 feet away from where it needs to connect into the pipe near the main shut off valve. So, my plan is to run CPVC (was PVC) lines to/from the main copper line.
My first step in this will be to splice into the main line, and I'd like to install a bypass near the main valve so that I can quickly bypass most of the new lines if there's a problem (immediately or in the future).
This first picture below is my main valve (the lever is behind the pipe on the left, feeding a pressure regulator in the middle, and then going back down on the right as it enters the house.
I want to cut into the line after the regulator, and then add the 3 valves to enable the bypass. Here's a very crude drawing, and below a picture of the pieces laid out on the floor as I'd connect them:
One problem, is lack of space because it's going to be in the wall (I will add any additional access panels as needed), and there's minimal space to the right of the existing plumbing:
My other option is to run the new bypass above the existing plumbing (requires that I open the wall above the current access panel).
Some questions:
(1) Are there any major concerns with this proposal?
(2) Does one solution here make more sense than the other?
(3) The current piping is 1" copper. I plan to make the run to/from the water softener with 1" CPVC. Would there be a big problem if I reduced the CPVC line to 3/4"?
Thank you,
-Alan
I'm attempting a DIY installation of a water softener. One problem is that the water softener needs to be mounted about 30 feet away from where it needs to connect into the pipe near the main shut off valve. So, my plan is to run CPVC (was PVC) lines to/from the main copper line.
My first step in this will be to splice into the main line, and I'd like to install a bypass near the main valve so that I can quickly bypass most of the new lines if there's a problem (immediately or in the future).
This first picture below is my main valve (the lever is behind the pipe on the left, feeding a pressure regulator in the middle, and then going back down on the right as it enters the house.
I want to cut into the line after the regulator, and then add the 3 valves to enable the bypass. Here's a very crude drawing, and below a picture of the pieces laid out on the floor as I'd connect them:
One problem, is lack of space because it's going to be in the wall (I will add any additional access panels as needed), and there's minimal space to the right of the existing plumbing:
My other option is to run the new bypass above the existing plumbing (requires that I open the wall above the current access panel).
Some questions:
(1) Are there any major concerns with this proposal?
(2) Does one solution here make more sense than the other?
(3) The current piping is 1" copper. I plan to make the run to/from the water softener with 1" CPVC. Would there be a big problem if I reduced the CPVC line to 3/4"?
Thank you,
-Alan
Last edited by a moderator: