tmy23
New Member
Greetings. I am about set to begin building the shower pan for a tile shower in a master bath conversion of what was a nursery, in a 130 year old victorian. Rough in's are done, subfloor secured, walls now straight, and will do framing this weekend, pour and form the shower pan next weekend. Here are some questions:
- Seems to me sill height is predicated (to a degree) on the thickness of the mud bed. The shower is 4' x 5'. I didn't want to cut into the joists which run cross the project, so roughed for an "end" drain, will probably put in a linear drain, seems to make the slope question simpler. Anyway...What is the minimum thickness (drain end) for the two mud layers? the slope will be 1.25 inches across the 5' dimension, so if I am 1" at the drain end, then I'm 2.25 at the top, then another 1" finish mud on top of the rubber barrier takes me to 3.25 at the top. BUT I don't know whether 1" at the low end, and then a uniform 1" for the top layer is enough. How high above the final tile height should the sill be?
Next question, I've been reading that generic Sakrete sand mix is acceptable for the mud layers, but that I have to pour the 2nd layer (rubber and then 2nd layer) within 16 hours and then tile within 16 hours on the finished layer or wait 28 days. Do I have this correct?
thanks in advance for all your help!!!
- Seems to me sill height is predicated (to a degree) on the thickness of the mud bed. The shower is 4' x 5'. I didn't want to cut into the joists which run cross the project, so roughed for an "end" drain, will probably put in a linear drain, seems to make the slope question simpler. Anyway...What is the minimum thickness (drain end) for the two mud layers? the slope will be 1.25 inches across the 5' dimension, so if I am 1" at the drain end, then I'm 2.25 at the top, then another 1" finish mud on top of the rubber barrier takes me to 3.25 at the top. BUT I don't know whether 1" at the low end, and then a uniform 1" for the top layer is enough. How high above the final tile height should the sill be?
Next question, I've been reading that generic Sakrete sand mix is acceptable for the mud layers, but that I have to pour the 2nd layer (rubber and then 2nd layer) within 16 hours and then tile within 16 hours on the finished layer or wait 28 days. Do I have this correct?
thanks in advance for all your help!!!