hhcibtpaun
Member
Hey Everyone,
Been here off and on for years. I am about to embark on my largest plumbing project to date
. Hoping to get some advice along the way. The project at hand is to replace all the copper piping in my house with PEX A (Expander fittings). The house in question was built in the Mid 1940's and a local plumber told me there is acidic water and many houses in the area have seen pinhole issues. I have most of the house gutted - at least where the plumbing is. So, I decided to replace it all. I watched a few You Tube videos and bought the Milwaukee Expander tool. The house has the following fixtures:
I still need to add lengths of the runs (everything will be home run) and height above meter in the chart above. From resources on this site I calculated 20.5 fixture units with 9 cold and 7 hot manifold connections. Before getting too far into the details, my first concern was the water meter coming into my basement. It looks like it comes in as 3/4, then is necked down to 1/2, then back to 3/4, then back to 1/2 (I think). See image below:
My plan was to run 3/4 PEX from the meter to the manifold. At first I was just going to take out the whole mess around the meter, then started thinking maybe I just leave it alone and upsize the 1/2" a few feet after it leaves the meter. I plan to do most things myself, but if the connections around the meter should be cleaned up, I would get a plumber or talk to the township. I assume they have some claim to the meter.
As I was pondering that I decided to get a pressure reading to baseline everything. So, I bought a SharkBite connector with a pressure gauge. I mounted it about 11 feet away from the meter, then ran a stub with cap out the other end. When I did that I get a pressure reading of 70 PSI.
So, my first few questions.
1. Is the 70 PSI high, or is the fact that I terminated right after the gauge and only have it 11 ft downstream giving me a high reading?
2. Do I get involved with cleaning up the mess of upsizes and downsizes around the meter? My neighbor apparently has the same mess.
3. If I keep the 1/2" coming out of the meter, do I upsize to 3/4" a few feet from the meter and take that to my manifold (maybe 20' away), or do I run 1/2" up to the manifold and then just upsize to 3/4" or 1" depending on what manifold is available? I am looking at something like this for the manifold. The 1" inlet is more readily available than the 3/4" version. Wondering if the upsizing will drop the pressures, or maybe they remain the same.
Thoughts and comments appreciated.
Thanks...Mike
Been here off and on for years. I am about to embark on my largest plumbing project to date
I still need to add lengths of the runs (everything will be home run) and height above meter in the chart above. From resources on this site I calculated 20.5 fixture units with 9 cold and 7 hot manifold connections. Before getting too far into the details, my first concern was the water meter coming into my basement. It looks like it comes in as 3/4, then is necked down to 1/2, then back to 3/4, then back to 1/2 (I think). See image below:
My plan was to run 3/4 PEX from the meter to the manifold. At first I was just going to take out the whole mess around the meter, then started thinking maybe I just leave it alone and upsize the 1/2" a few feet after it leaves the meter. I plan to do most things myself, but if the connections around the meter should be cleaned up, I would get a plumber or talk to the township. I assume they have some claim to the meter.
As I was pondering that I decided to get a pressure reading to baseline everything. So, I bought a SharkBite connector with a pressure gauge. I mounted it about 11 feet away from the meter, then ran a stub with cap out the other end. When I did that I get a pressure reading of 70 PSI.
So, my first few questions.
1. Is the 70 PSI high, or is the fact that I terminated right after the gauge and only have it 11 ft downstream giving me a high reading?
2. Do I get involved with cleaning up the mess of upsizes and downsizes around the meter? My neighbor apparently has the same mess.
3. If I keep the 1/2" coming out of the meter, do I upsize to 3/4" a few feet from the meter and take that to my manifold (maybe 20' away), or do I run 1/2" up to the manifold and then just upsize to 3/4" or 1" depending on what manifold is available? I am looking at something like this for the manifold. The 1" inlet is more readily available than the 3/4" version. Wondering if the upsizing will drop the pressures, or maybe they remain the same.
Thoughts and comments appreciated.
Thanks...Mike