Hello! I'm building a mudroom that will hold a furnace, water heater, laundry sink, washing machine, and toilet.
I'm trying to design my rough in before we pour concrete so I can start digging once I get my permits this week as it's slab foundation with 42" footings.
So my couple things are
A. (Vent for toilet) I need to sleeve through the footing with my 3" main. The wall I come through the footing is the water closet with my toilet. Can I branch off the 3" line with a 2" pipe at a 45° to go through the slab and slightly into the footing before the toilet where itll be inside my wall and go through the roof?
B. (Washer vent) can I use a studor vent for the washing machine or do I need to tie the vents together?
Attached is my plans, one blank and one I drew on. Blue being drains and red veing vents.
I'm trying to design my rough in before we pour concrete so I can start digging once I get my permits this week as it's slab foundation with 42" footings.
So my couple things are
A. (Vent for toilet) I need to sleeve through the footing with my 3" main. The wall I come through the footing is the water closet with my toilet. Can I branch off the 3" line with a 2" pipe at a 45° to go through the slab and slightly into the footing before the toilet where itll be inside my wall and go through the roof?
B. (Washer vent) can I use a studor vent for the washing machine or do I need to tie the vents together?
Attached is my plans, one blank and one I drew on. Blue being drains and red veing vents.