Brendan Poirier
New Member
I did my basement slab plumbing last winter. Continuing on the project this year and I will be doing the floor tile in the next month or so.
We are on a septic tank so we had to install a sewage ejector pit. The photo here shows the routing of the shower to the left and the washer will be next to the jackhammer. From the main 3 inch line I ran a 2 inch drain to the fork in the slab, then a WYE and a 2 inch drain to each the shower and the washer. Each fixture will have their own 2 inch vent, connecting above the shower and sharing a 2 inch riser to the attic before connecting to the main 3 inch stack for venting.
the 2 inch section running from the WYE to the main is about 5 feet before it goes to 3 inch.
I am now realizing that maybe using a 2 inch pipe to connect the 2 fixtures tot he main 3 inch drain was a bad move and it should have been 3 inch. According to NPC (Canada) , this is allowed as a washer is counted as 2 DFU and the shower as 2 DFU with the 2 inch pipe being able to handle 4 DFU
My main concern is the pipe being overloaded if both were being used simultaneously. If this needs to be fixed, now is the time before I tile the floor.
Looking for some input.
We are on a septic tank so we had to install a sewage ejector pit. The photo here shows the routing of the shower to the left and the washer will be next to the jackhammer. From the main 3 inch line I ran a 2 inch drain to the fork in the slab, then a WYE and a 2 inch drain to each the shower and the washer. Each fixture will have their own 2 inch vent, connecting above the shower and sharing a 2 inch riser to the attic before connecting to the main 3 inch stack for venting.
the 2 inch section running from the WYE to the main is about 5 feet before it goes to 3 inch.
I am now realizing that maybe using a 2 inch pipe to connect the 2 fixtures tot he main 3 inch drain was a bad move and it should have been 3 inch. According to NPC (Canada) , this is allowed as a washer is counted as 2 DFU and the shower as 2 DFU with the 2 inch pipe being able to handle 4 DFU
My main concern is the pipe being overloaded if both were being used simultaneously. If this needs to be fixed, now is the time before I tile the floor.
Looking for some input.