Tommy Fox
New Member
I am looking to plumb a new addition (one story with full basement) to my house.
I have started to put things together, but I wanted to get some validation before I go further.
The addition has a kitchen and a mudroom.
The interesting thing about this addition is that part of its floor cantilever over the back wall of garage.
The cantilever section is about 3 ft above the garage floor.
So far, I have constructed the stack and a main line.
The stack goes into an existing cast iron hub with a rubber boot.
The 4-3 wye at bottom of stack is for future expansion, in case I have plumbing needs in the basement.
The 3 in test tee is for testing and trouble shooting.
I plan to cap the top of the stack as each fixture will be individually vented, thus no need to have a vent on the stack. Is this correct?
The connection to the bathroom sink is not made yet. The open 2 in 90 elbow is where it will catch the 2 in pipe from the sink. I'm using a 2 in because the toilet will be wet vented by the sink. Sink drain is normally 1.5 in, but because of it serving as a wet vent for the toilet, I am required to up it to 2in. Correct?
I need some advice on the pipe hanger. As you can see, they are too short. My plan is to put cross 2x4 into the joist bay, and hang the hanger from there. What's the right way to extend the hanger? Can I just use some steel wire?
The toilet plumbing is constructed as follows.
From the top, 4-3 coupler, then 2 street 45, then 3x2 wye (to catch the bathroom sink), finally into a 3x3 combo.
My plan for the toilet connection is to use a 3-in flange that fits inside a regular 4in pipe, this 4-in pipe goes into 4-3 coupler. I like this better than just a 3-in flange fitting outside a 3-in pipe, because it seems to have less chance of a leak.
Last picture is the section into the garage under the cantilever
I am running this main line via the garage because I don't want to cut into the I-joist or hang it below the joist inside the basement.
I am in NJ, the garage is unheated.
Since this is just the drain line, I believe it is ok to run the line via an unconditioned space. Correct?
Eventually I plan to frame a knee wall for the cantilever, in which case, it would make this section essentially the same as in the basement.
Thank you in advance for all your advice.
I have started to put things together, but I wanted to get some validation before I go further.
The addition has a kitchen and a mudroom.
The interesting thing about this addition is that part of its floor cantilever over the back wall of garage.
The cantilever section is about 3 ft above the garage floor.
So far, I have constructed the stack and a main line.
The stack goes into an existing cast iron hub with a rubber boot.
The 4-3 wye at bottom of stack is for future expansion, in case I have plumbing needs in the basement.
The 3 in test tee is for testing and trouble shooting.
I plan to cap the top of the stack as each fixture will be individually vented, thus no need to have a vent on the stack. Is this correct?
The connection to the bathroom sink is not made yet. The open 2 in 90 elbow is where it will catch the 2 in pipe from the sink. I'm using a 2 in because the toilet will be wet vented by the sink. Sink drain is normally 1.5 in, but because of it serving as a wet vent for the toilet, I am required to up it to 2in. Correct?
I need some advice on the pipe hanger. As you can see, they are too short. My plan is to put cross 2x4 into the joist bay, and hang the hanger from there. What's the right way to extend the hanger? Can I just use some steel wire?
The toilet plumbing is constructed as follows.
From the top, 4-3 coupler, then 2 street 45, then 3x2 wye (to catch the bathroom sink), finally into a 3x3 combo.
My plan for the toilet connection is to use a 3-in flange that fits inside a regular 4in pipe, this 4-in pipe goes into 4-3 coupler. I like this better than just a 3-in flange fitting outside a 3-in pipe, because it seems to have less chance of a leak.
Last picture is the section into the garage under the cantilever
I am running this main line via the garage because I don't want to cut into the I-joist or hang it below the joist inside the basement.
I am in NJ, the garage is unheated.
Since this is just the drain line, I believe it is ok to run the line via an unconditioned space. Correct?
Eventually I plan to frame a knee wall for the cantilever, in which case, it would make this section essentially the same as in the basement.
Thank you in advance for all your advice.