Please provide guidance or preference on where to place a clean out. I interpret the code to need a 4" clean out for the 4" line and the toilet cannot be considered a clean out. I can either place the clean out at the number 1 spot by extending the 4" line (before the 2" transition) or place it at the number 2 spot. My question is based on whether I need to have the clean out before the 45 fitting. I would prefer to have it in the straight section if that is allowed.
See the attachment.
Clean out will be flush mounted with the slab.
Anderson County, SC
Slab on grade, underground rough in.
See the attachment.
Clean out will be flush mounted with the slab.
Anderson County, SC
Slab on grade, underground rough in.