Greetings, I need to run 3" pvc through several 2x10 floor joists. I have checked the code and I need to be 2" from top and bottom of Joist with my hole and hole can not be more then 1/3 of depth of joist (which this will be). I understand that I should sister 2x4 material to the joists. Could anyone tell me how long the 2x4's should be and can it be above or below the hole. Glued, nailed, screwed? Any other tips on installing the sisters?

Thanks!
Steve
 

Bob NH

In the Trades
Messages
3,310
Reaction score
9
Points
0
Location
New Hampshire
Structural Solutions

The problem will be in developing the joint strength between the 2x4 and the 2x10. I would put a 4-foot 2x4 edge against the 2x10 with the wide part against the subfloor if there is one. I would use glue with some water resistance and attach the part with three inch "drywall" screws on 4" spacing from the 2x10 side, and to the subfloor with appropriate screw length. You will probably also put one on the bottom.

Actually, the weakening is not as great as it would appear because of some structural arithmetic that I won't cover here.

The hole can cause the 2x10 to split through the hole because of shear stresses. I would reinforce the area around the hole with about a 16" length of 5/8 or 3/4 plywood, full depth, glued and screwed to the side of the 2x10 opposite the side where you put the 2x4's. I would slip the plywood over the pipe when installing the pipe but not fasten it until you get the pipe run, so it will be easier to get the pipe through.

You are going to have a tough time because it will be difficult to get any significant length through the joists. I would design a reinforcement to be installed after the pipe that would let me notch the bottom of the joists and bring the pipe up from the bottom. That would shock the building inspector but it could be made stronger than the original. The result would be a lot like the fabricated joists that you see a lot of these days.

You will need to support the joists before you cut if the joists are supporting heavy loads now. Most floors are designed for 40 lbs per sq ft and may have only about 10 lbs per square ft on them, so you don't have to worry if the loads are light and you are only cutting a couple of joists.

The details of the design would depend on how close the pipe ends up to the upper and lower edges of the joist, and whether you have a ceiling attached to the joists.
 

Sulconst2

New Member
Messages
205
Reaction score
2
Points
0
Location
old bridge nj
had a situation with an oversize cut thru a joist that failed frame inspection. needed to install a piece of steel around the pipe with a pair of bolts on both ends. used cardboard to make a template and brought it to a steel yard. piece was only about 30" long and 1/2" thick. just short of joist hieght for play. passed!
 
Top
Hey, wait a minute.

This is awkward, but...

It looks like you're using an ad blocker. We get it, but (1) terrylove.com can't live without ads, and (2) ad blockers can cause issues with videos and comments. If you'd like to support the site, please allow ads.

If any particular ad is your REASON for blocking ads, please let us know. We might be able to do something about it. Thanks.
I've Disabled AdBlock    No Thanks