Hi, I am remodeling a poorly done, garage conversion that has a unvented bath at the end of it.
-Per the picture, I am removing a tub, and installing a shower with the drain and water lines on an interior partition wall (was outside wall before).
-The old lav drain went strait up into the vanity furniture from the floor! I am turning the vanity 90 degrees and moving the drain to an interior partition wall, and . That drain will vent strait up through the roof.
-The toilet is shifting left about 10", I am using two 45's to accomplish this. should be ok right?
Question is if this wet vent scenario work or do I need to vent the shower up into the attic (and attach to lav vent up there) or is it close enough to wet vent.
I would have a mix of both 2" and 3" horizontal drains to get to the vent. Everything currently ties together below the toilet through what looks like a 3" cross.
From the lav drain to the toilet the total distance is 76" (40 x 2"pipe + 36" x 3" pipe) and from the shower drain to the toilet (end of wet vent) it would be 77" (31" x 3" pipe + 46" x 2" pipe)
Would that meet code? Alternatives?
Thanks
-Per the picture, I am removing a tub, and installing a shower with the drain and water lines on an interior partition wall (was outside wall before).
-The old lav drain went strait up into the vanity furniture from the floor! I am turning the vanity 90 degrees and moving the drain to an interior partition wall, and . That drain will vent strait up through the roof.
-The toilet is shifting left about 10", I am using two 45's to accomplish this. should be ok right?
Question is if this wet vent scenario work or do I need to vent the shower up into the attic (and attach to lav vent up there) or is it close enough to wet vent.
I would have a mix of both 2" and 3" horizontal drains to get to the vent. Everything currently ties together below the toilet through what looks like a 3" cross.
From the lav drain to the toilet the total distance is 76" (40 x 2"pipe + 36" x 3" pipe) and from the shower drain to the toilet (end of wet vent) it would be 77" (31" x 3" pipe + 46" x 2" pipe)
Would that meet code? Alternatives?
Thanks