    I've read through a lot of different posts and I think I have came up with the correct venting and drain configuration. I'm not very good at drawing so hopefully it makes sense. My vanity, toilet and tub are all along the same wall that is about 10' feet long.

    The main sewer line comes up directly under the wall behind the toilet. So the main line comes up and vents up through the wall behind the toilet. I think i need a double combination y-1/8 bend for the bottom drain and a san tee for the upper vent split.

    One edit... the sanitary tee for the vent should be turned upside down. Not correct in picture

    Thank you for spending the time to look at my question.

    Rob

    Attached Files:

    Last edited: Jul 5, 2010
  2. Terry

    Terry Administrator Staff Member

    Messages:
    15,050
    Location:
    Bothell, Washington
    When you turn the vent cross over in the drawing you will be fine.

    Below is an example of two story plumbing

    [​IMG]
    Last edited: Jul 5, 2010
  3. arfeller

    arfeller New Member

    Messages:
    77
    Location:
    Port Angeles, WA
    Thank you Terry.

    I have been told several times that the sanitary tee is acceptable to use for two drains into a vertical stack. I currently have a double y with two 45's for the drain. Would a sanitary tee be acceptable here?
  4. Terry

    Terry Administrator Staff Member

    Messages:
    15,050
    Location:
    Bothell, Washington
    A sanitary doube tee would work under the toilet, pretty common in fact.
    Merlin Blue used to plumb his that way.

    As you can see from my drawing, I like to keep the 2" lines tighter to the main stack, and then trap arm over with 1-1/2".
    I use more wyes adn keep everything tighter.
    That cuts up the framing less. The framers loved me and used to ask me why the others plumbers didn't do layout the way I did. The answer, they didn't car how much wood got taken out.
  5. arfeller

    arfeller New Member

    Messages:
    77
    Location:
    Port Angeles, WA
    I appreciate the reply. Very helpful.

    Thank you!
Similar Threads: Proposed drain
Forum Title Date
UPC Plumbing Code Questions My drain was plumbed to my next door neighbors sewage pump. Jun 23, 2014
UPC Plumbing Code Questions UPC codes with respect to Linear Drains Jun 17, 2014
UPC Plumbing Code Questions remodeling and want to make a change to my drain lines May 20, 2014
UPC Plumbing Code Questions Washing Machine Draining Hose Question Oct 19, 2012
UPC Plumbing Code Questions drain slope question - UPC May 11, 2012

Share This Page