    I am finishing my basement in my newly constructed home. I have completed all the framing and electrical runs, and am now ready to install the grid system for the suspended ceiling.

    I will be using 2x2 ceiling tiles. For a 2x2 installation, it's my understanding that the standard way to install the grids is to:

    1) Align the main tees parallel & 48" on center,
    2) Install 48" cross tees 24" OC & perpendicular to the main tees, and
    3) Install 24" cross tees perpendicular and centered on the 48" cross tees.

    My question: Can I simply install the main tees 24" on center, and then install the 24" cross tees perpendicular and 24" OC on the main tees, thereby eliminating the need for the 48" cross tees?

    Is there anything "wrong" with installing the grid as I describe in my question?

    Thank you very much for your time and consideration.
  2. alexjag33

    alexjag33 New Member

    Messages:
    32
    Drywall

    Um, you might want to drywall first.

    I've never installed a grid prior to the drywall.

    The outer tracks for your suspended ceiling should be fastened to drywall, not studs.

    The rest of your installation steps look OK.
  3. thebrownsfan

    thebrownsfan New Member

    Messages:
    6
    LOL! Oh, I am with you, Alex, I know about the drywall part...I was just referring to post-drywall installation.....thanx, however for making sure! :)

    Todd
  4. jimbo

    jimbo Plumber

    Messages:
    8,997
    Location:
    San Diego
    Having done only a small amount of this, it occurs to me that it may be slightly more tedious to install in the manner you describe. It is just something rattling around in my pea brain, and hopefully someone with a lot of experience can shed some light. As far as the final outcome, I don't see a big difference between the two methods.
  5. Rmodeler

    Rmodeler Junior Member

    Messages:
    8
    Location:
    Indiana
    You would have twice the number of main runners to hang/wire up, plus it will cost you more. Check the cost of one main runner versus 3 4' cross tees. You can put in 3 4' cross tees quicker than hanging one main runner. It would be a lot of unnecessary work.
  6. jimbo

    jimbo Plumber

    Messages:
    8,997
    Location:
    San Diego
    Thanks, remodeler....that is sort of what I was thinking but you put it in very epecific terms for us.
  7. alexjag33

    alexjag33 New Member

    Messages:
    32
    Browns

    Oh, and by the way, GO BROWNS! :D
  8. AcidWater

    AcidWater New Member

    Messages:
    123
    Location:
    .
    Your grid pieces have some thickness, and you must account for that -- 24" OC will add up to an error by the time you reach the opposite wall. Check that the tiles are actually less than 24" to account for that, if you can do 24" OC.
  9. thebrownsfan

    thebrownsfan New Member

    Messages:
    6
    I'm with ya, Acid. Already have that taken into account.....BTW, I will be installing the main tees on 48" centers, then adding the 48" and 24" crosses where needed....

    Just want to say that this forum has been great for me over the years with all the knowledge and advice help. Thanx, all!!
Similar Threads: Installing suspended
Forum Title Date
Remodel Forum & Blog Installing a single oven below the counter. Anyone done this? What size base cabinet? Jun 4, 2014
Remodel Forum & Blog I am thinking of installing these allen + roth slate tiles... But.. Apr 25, 2014
Remodel Forum & Blog Installing a dryer soffit vent & Clearing a blocked existing dryer line (photos) Nov 28, 2013
Remodel Forum & Blog Installing tile in bathroom - Any tips? Aug 24, 2011
Remodel Forum & Blog Installing Pergo laminate flooring Feb 17, 2010

Share This Page