    OK, this is my first drop in frame.

    Water damaged sub-floor repaired, joists reinforced with blocking, even put sound proof insulation down.
    Now I have a question on the correct height for the drop-in tub.
    Here it goes.
    Height of the tub deck is 19", lip edge is 2" so the height from the floor to deck lip edge is 17". Now for the vertical frame calculation using 2x4s: Bottom plate 1 1/2, top plate 1 1/2, plywood 3/4, cement board 1/2, tile & mortar 1/2, vertical 2x4s at 12 1/4. This gives me a height of 17". Bottom of deck lip edge is 17" so I should be good, right? (1 1/2, 1 1/2, 3/4, 1/2, 1/2, 12 1/4, = 17) What I did not calculate is the mortar bed the whirlpool will sit in. Do I add another inch for the mortar bed? Meaning the height to the deck lower lip would be 18" and my frame needs to come up another inch? Or do I ignore the mortar bed with the idea that pushing down into the bed will displace enough mortar to make the bottom of the whirlpool practically sit on the sub-floor. The whirlpool is a jacuzzi primo if that matters. comments &/or suggestion appreciated.

    questions:
    1. Am I building to the correct height?
    2. Do I mortar & tile after setting the tub in mortar bed or before? (current plan is to set in mortar bed first & use 1" scrap wood to leave space for the cement board & tile & mortar.
     
  2. johnfrwhipple

    johnfrwhipple BATHROOM DESIGN & BUILD for both Canada & the US

    Joined:
    Jul 20, 2009
    Occupation:
    Design Work World Wide: Bathrooms Vancouver Area
    Location:
    North Vancouver, BC
    If you can tile the tub deck first that is dream. Then your life will be easier.

    If you want to tile after then 5/8" spacers work well for 3/8" tile and 1/4" thin-set.

    The mortar mix under the tub should be higher than needed. The tub set overtop and squished down to resting position. The tub should sit on it's feet and the mortar mix serves as only bonus strength between the feet.

    We use poly to keep the mortar from bonding to the tub.

    Just installed one yesterday.

    I'll look for the pics.

    JW
     
  3. Sponsor

    Sponsor Paid Advertisement

     
  4. johnfrwhipple

    johnfrwhipple BATHROOM DESIGN & BUILD for both Canada & the US

    Joined:
    Jul 20, 2009
    Occupation:
    Design Work World Wide: Bathrooms Vancouver Area
    Location:
    North Vancouver, BC
    [​IMG]

    Here you can see the tub sitting out in the room over some Ditra. There is about 2"-3" of space under the tub when it's resting on it's feet.

    [​IMG]

    My mortar mix mixed fluffy and sitting nearly double the height I need.

    [​IMG]

    I have the mix in the middle away from the feet of the tub.

    [​IMG]

    Then a double layer of light weight poly and the tub goes in over top.

    From the face and sides I can push the poly back and pack the mortar mix.

    All good.

    JW
     
  5. Cookie

    Cookie .

    Joined:
    Oct 7, 2005
    Location:
    .
    Pictures look good John. Mine didn't require mortar though, some do not.
     
  6. clapfc

    clapfc New Member

    Joined:
    Nov 27, 2012
    Occupation:
    professional
    Location:
    albany ny
    JW, thank you for the response and the pics. I get nervous when measurements have to be exact especially the first time I am doing something. This really helps. Gives me confidence I am on the right track. Did not think about the poly, I will incorporate that into the project. Pics really helped. Thanks again
     
  7. johnfrwhipple

    johnfrwhipple BATHROOM DESIGN & BUILD for both Canada & the US

    Joined:
    Jul 20, 2009
    Occupation:
    Design Work World Wide: Bathrooms Vancouver Area
    Location:
    North Vancouver, BC

    Your welcome.

    The poly is key. Once you set that tub run it through it's paces. If you need to remove it because of a leak you will be glad the tub is not stuck to the poly. The poly is a bond breaker here.

    The mortar mix does not hold up the tub but only prevents it from sagging in the middle. It will feel more solid this way.

    JW
     
Similar Threads: Drop frame
Forum Title Date
Shower & Bathtub Forum & Blog Drop in water pressure when flushing toilet Jul 18, 2015
Shower & Bathtub Forum & Blog Drop-in tub rim - no overhang Mar 20, 2015
Shower & Bathtub Forum & Blog Help please. Is this right? Drop in tub tile gap. Jan 16, 2015
Shower & Bathtub Forum & Blog Need your input. Noble TS - drop down shower Dec 30, 2014
Shower & Bathtub Forum & Blog Shower pressure dropped and noise increased Jun 7, 2014

Share This Page