Hi,
I have a rental property that had two units but one 200 amp panel. I paid electricians a lot of money to split it to two meters and then two panels.
I requested the original 200 amp panel to be discarded (it had 40 spaces) and replaced with a 24 or 30 space 125 amp main breaker panel. I asked for the 2nd unit that was getting it's own (new) panel to get a 125 amp 20 or 24 space main breaker panel as well. My understanding was this was ok because load varies and not all circuits are on at all times. The electricians agreed to this plan.
During installation, I was told they didn't make 125 amp breaker panels with 30 spaces. The plan was to use a 125 amp main lug panel with 30 spaces and put the main breaker in one of the circuits (split bus??). I was told it would be labeled as main. I was told the 2nd panel was no problem to purchase as a 20 space 125 amp panel was easy to get.
I asked what size feeders they were running to each panel and I believe they said 2/0. I asked if 2/0 could handle 125 amp and was told yes. I think they said the service cable was 4/0.
Before the work started, I emailed the company and told them that after the split, I was going to install a new tankless H2O heater in the 2nd unit. The requirements per the manufacturer were 125 amp panel with a 60 amp double pole breaker and a #6-2 wire.
After the job was complete, here's what I got: same 200 amp breaker panel with a 100 amp main breaker on the bus. In the 2nd unit I got a 20 space 100 amp main breaker panel. I have not paid these guys yet.
I cannot believe they did this after we talked about two 125 amp panels. Then the electrician said he re-installed the old panel with the main breaker on the bus because he couldn't find the main lug 125 amp 30 space panel. He didn't discuss this change with me.
Not sure why I got two 100 amp panels when I asked for two 125 amps. This was done Friday and I emailed them my concerns.
Is it feasible to have 2 125 amp panels with a 200 amp service? If it's not feasible, then I wish they would have told me before doing all this work. Now I wonder if they even put in the correct size of wire necessary to feed 125 amp panels.
Thanks for any advise you can give...
I have a rental property that had two units but one 200 amp panel. I paid electricians a lot of money to split it to two meters and then two panels.
I requested the original 200 amp panel to be discarded (it had 40 spaces) and replaced with a 24 or 30 space 125 amp main breaker panel. I asked for the 2nd unit that was getting it's own (new) panel to get a 125 amp 20 or 24 space main breaker panel as well. My understanding was this was ok because load varies and not all circuits are on at all times. The electricians agreed to this plan.
During installation, I was told they didn't make 125 amp breaker panels with 30 spaces. The plan was to use a 125 amp main lug panel with 30 spaces and put the main breaker in one of the circuits (split bus??). I was told it would be labeled as main. I was told the 2nd panel was no problem to purchase as a 20 space 125 amp panel was easy to get.
I asked what size feeders they were running to each panel and I believe they said 2/0. I asked if 2/0 could handle 125 amp and was told yes. I think they said the service cable was 4/0.
Before the work started, I emailed the company and told them that after the split, I was going to install a new tankless H2O heater in the 2nd unit. The requirements per the manufacturer were 125 amp panel with a 60 amp double pole breaker and a #6-2 wire.
After the job was complete, here's what I got: same 200 amp breaker panel with a 100 amp main breaker on the bus. In the 2nd unit I got a 20 space 100 amp main breaker panel. I have not paid these guys yet.
I cannot believe they did this after we talked about two 125 amp panels. Then the electrician said he re-installed the old panel with the main breaker on the bus because he couldn't find the main lug 125 amp 30 space panel. He didn't discuss this change with me.
Not sure why I got two 100 amp panels when I asked for two 125 amps. This was done Friday and I emailed them my concerns.
Is it feasible to have 2 125 amp panels with a 200 amp service? If it's not feasible, then I wish they would have told me before doing all this work. Now I wonder if they even put in the correct size of wire necessary to feed 125 amp panels.
Thanks for any advise you can give...
Last edited: